Walter & Eliza Hall Institute (WEHI) – Chilled Water Plant Upgrade.

Walter & Eliza Hall Institute (WEHI) – Chilled Water Plant Upgrade. Mechanical Services Value - $2,900,000

Project Managers – Hooker Cockram.

Mechanical Consultant – S2F.

Architect - Denton Corker Marshall

Installation of 3 x 2800Kw Dalkia chillers, BAC Towers,
fitment of 350mm ABS pipe risers through 8 levels of
existing building. Complete layout of plant and
coordination of works to ensure the building maintained
CHW supply with interruptions kept to a minimum of
hours. Coordinate the strip down of new chillers to
facilitate the fitment through a set of standard double
doors.